Steps
1. Lay out and mark transition areas to be milled parallel to existing surfaces to remain.
2. Mill existing asphalt as specified per contract.
3. Clean the milled area and dispose of all debris offsite.
4. Some areas may not be milled due to the large size of the equipment.
NOTE:
 Edge Milling is utilized to insure a smooth transition between the new asphalt overlay and existing gutter pans and tie-ins.