Steps
1. Clean parking lot with high power blowers and brooms.
2. Oil spots will be treated with an oil primer to improve adhesion of the sealer. (Sealer will not bond to heavily soiled areas)
3.
Two coats
 of Seal Master brand
Master Seal
 asphalt sealer will be applied to the parking lot. 
Master Seal
 is a  mineral reinforced, clay stabilized asphalt emulsion.
4. If contract calls for striping, parking lot will be striped when sealer dries.
5. Parking lot can be re-opened 36 hours after the final coat of sealer has been applied.
Traffic Management:
 Owner is responsible for clearing parking area before operation begins and insuring parking lot stays closed during the sealcoating operation and while sealer dries.